The cost of a house in Lahore comes down to two numbers: the covered area you build and the rate per square foot. On published 2026 market benchmarks, the grey structure of a 1,800 sq ft 5 marla house works out to about PKR 50.4 – 57.6 lakh, a 3,200 sq ft 10 marla house about PKR 89.6 lakh – 1.02 crore, and a 5,500 sq ft 1 kanal house about PKR 1.54 – 1.76 crore. These are market ranges, not a quotation: Danial Khan & Associates prices each project individually, because the real figure depends on structural design, specifications, site conditions and finish level.
Step 1: your covered area
Construction is priced on covered area, the total floor area of every storey you build, not on plot size. A double-storey house has a covered area larger than its plot, and a basement adds more. Your architect's floor plans give the exact figure; before you have drawings, your society's building bylaws tell you how much of the plot each floor may cover.
Plot sizes differ with the marla standard. DHA, Bahria Town and most planned Lahore societies count a marla as 225 sq ft; older areas and land records use 272.25 sq ft. Check your allotment letter, or use the marla to square feet converter.
| Plot | Sq ft (225 sq ft marla) | Sq ft (272.25 sq ft marla) | Common plot (225) |
|---|---|---|---|
| 5 Marla | 1,125 | 1,361.25 | 25 × 45 ft |
| 10 Marla | 2,250 | 2,722.5 | 35 × 65 ft |
| 1 Kanal | 4,500 | 5,445 | 50 × 90 ft |
Step 2: what the rate includes
Ask every contractor what their rate covers. Quotations in Lahore are normally given at one of two levels:
- Grey structure. Foundations, the structural frame and roof slabs, brickwork, plaster, and the concealed electrical conduits and plumbing lines. The materials are cement, steel, bricks, sand, crush and concrete. Benchmark: PKR 2,800–3,200 per sq ft.
- Complete construction. Grey structure plus finishing: tiles and flooring, paint, doors and windows, sanitary fittings, the kitchen and wardrobes, and electrical fixtures. Benchmark: PKR 3,500–4,200 per sq ft with a standard finish, rising to PKR 5,000–6,500 for a luxury or custom finish. This is where the choice of brands and grades moves the total most.
A turnkey contract covers design, structure and finishing together. When you compare two quotations, compare them at the same level and against the same list of specified brands and grades.
5 Marla house construction cost
2026 Lahore benchmarksA 5 marla plot is 1,125 sq ft on the 225 sq ft marla. Find the row nearest your covered area; each cell is that area multiplied by the benchmark range for the finish level. For a 1,800 sq ft covered area that is about PKR 50.4 – 57.6 lakh for the grey structure and PKR 63.0 – 75.6 lakh complete with a standard finish.
| Covered area | Grey Structure (PKR) 2,800–3,200 / sq ft | Standard Finish (PKR) 3,500–4,200 / sq ft | Premium Finish (PKR) 4,200–5,000 / sq ft | Luxury / Custom (PKR) 5,000–6,500 / sq ft |
|---|---|---|---|---|
| 1,500 sq ft | 42.0 – 48.0 lakh | 52.5 – 63.0 lakh | 63.0 – 75.0 lakh | 75.0 – 97.5 lakh |
| 1,800 sq ft | 50.4 – 57.6 lakh | 63.0 – 75.6 lakh | 75.6 – 90.0 lakh | 90.0 lakh – 1.17 crore |
| 2,100 sq ft | 58.8 – 67.2 lakh | 73.5 – 88.2 lakh | 88.2 lakh – 1.05 crore | 1.05 – 1.36 crore |
| 2,400 sq ft | 67.2 – 76.8 lakh | 84.0 lakh – 1.01 crore | 1.01 – 1.20 crore | 1.20 – 1.56 crore |
10 Marla house construction cost
2026 Lahore benchmarksA 10 marla plot is 2,250 sq ft on the 225 sq ft marla. Find the row nearest your covered area; each cell is that area multiplied by the benchmark range for the finish level. For a 3,200 sq ft covered area that is about PKR 89.6 lakh – 1.02 crore for the grey structure and PKR 1.12 – 1.34 crore complete with a standard finish.
| Covered area | Grey Structure (PKR) 2,800–3,200 / sq ft | Standard Finish (PKR) 3,500–4,200 / sq ft | Premium Finish (PKR) 4,200–5,000 / sq ft | Luxury / Custom (PKR) 5,000–6,500 / sq ft |
|---|---|---|---|---|
| 2,800 sq ft | 78.4 – 89.6 lakh | 98.0 lakh – 1.18 crore | 1.18 – 1.40 crore | 1.40 – 1.82 crore |
| 3,200 sq ft | 89.6 lakh – 1.02 crore | 1.12 – 1.34 crore | 1.34 – 1.60 crore | 1.60 – 2.08 crore |
| 3,600 sq ft | 1.01 – 1.15 crore | 1.26 – 1.51 crore | 1.51 – 1.80 crore | 1.80 – 2.34 crore |
| 4,000 sq ft | 1.12 – 1.28 crore | 1.40 – 1.68 crore | 1.68 – 2.00 crore | 2.00 – 2.60 crore |
1 Kanal house construction cost
2026 Lahore benchmarksA 1 kanal plot is 4,500 sq ft on the 225 sq ft marla. Find the row nearest your covered area; each cell is that area multiplied by the benchmark range for the finish level. For a 5,500 sq ft covered area that is about PKR 1.54 – 1.76 crore for the grey structure and PKR 1.93 – 2.31 crore complete with a standard finish.
| Covered area | Grey Structure (PKR) 2,800–3,200 / sq ft | Standard Finish (PKR) 3,500–4,200 / sq ft | Premium Finish (PKR) 4,200–5,000 / sq ft | Luxury / Custom (PKR) 5,000–6,500 / sq ft |
|---|---|---|---|---|
| 4,500 sq ft | 1.26 – 1.44 crore | 1.57 – 1.89 crore | 1.89 – 2.25 crore | 2.25 – 2.92 crore |
| 5,500 sq ft | 1.54 – 1.76 crore | 1.93 – 2.31 crore | 2.31 – 2.75 crore | 2.75 – 3.58 crore |
| 6,500 sq ft | 1.82 – 2.08 crore | 2.27 – 2.73 crore | 2.73 – 3.25 crore | 3.25 – 4.22 crore |
| 7,500 sq ft | 2.10 – 2.40 crore | 2.63 – 3.15 crore | 3.15 – 3.75 crore | 3.75 – 4.88 crore |
Estimate your own house
Your covered area, your rateRates are the published 2026 market benchmark ranges for Lahore used by our project estimator, where the sources are named. They are general market ranges, not prices offered by Danial Khan & Associates, and they exclude the architect's design fee (benchmark PKR 35–150 per sq ft), interiors and furniture, and external works. 1 lakh = 100,000; 1 crore = 100 lakh.
An estimate from market benchmarks or from the rate you enter. It is not a quotation from Danial Khan & Associates.
For a floor-by-floor estimate use the project estimator, or work backwards from a budget with the budget-based build size calculator. The brick and material calculator estimates bricks, cement and steel for the same covered area.
What moves the total
- Structural design. Soil conditions, a basement, large spans and double-height spaces change the quantity of steel and concrete.
- Specifications. The grade of steel and cement, and the brands of tiles, sanitary ware, wood and fittings.
- Finish level. A standard finish and a fully designed interior are very different budgets on the same grey structure.
- Site conditions. Access, filling and levelling, and the society's own requirements.
- Items outside the house. Boundary wall, water tanks, solar, and external works are often quoted separately. See the boundary wall, water tank and solar calculators.
On our own projects, brands and grades are selected per project and confirmed with you before ordering, and nothing is substituted without your sign-off.
How long it takes
By phase| Phase | Typical duration |
|---|---|
| Design | 3–4 weeks |
| Working drawings | 2–3 weeks |
| Grey structure | 4–6 months |
| Finishing | 2–3 months |
| Turnkey (design + build) | 8–12 months |
Durations vary with project size, scope, approvals, material selections and site conditions.
Get a quotation for your plot
A project-specific quotation needs your plot size, location and the level of finish you want. Send them over and we will come back with the next step, or book a site visit.
Frequently asked questions
On published 2026 market benchmarks, about PKR 50.4 – 57.6 lakh for the grey structure of a 1,800 sq ft covered area, and PKR 63.0 – 75.6 lakh complete with a standard finish. Multiply your own covered area by the benchmark rates to adjust it; the actual cost depends on structural design, specifications, site conditions and finish level.
On published 2026 market benchmarks, about PKR 89.6 lakh – 1.02 crore for the grey structure of a 3,200 sq ft covered area, and PKR 1.12 – 1.34 crore complete with a standard finish. Multiply your own covered area by the benchmark rates to adjust it; the actual cost depends on structural design, specifications, site conditions and finish level.
On published 2026 market benchmarks, about PKR 1.54 – 1.76 crore for the grey structure of a 5,500 sq ft covered area, and PKR 1.93 – 2.31 crore complete with a standard finish. Multiply your own covered area by the benchmark rates to adjust it; the actual cost depends on structural design, specifications, site conditions and finish level.
The 2026 market benchmark is PKR 2,800–3,200 per sq ft of covered area. Complete construction is 3,500–6,500 per sq ft depending on the finish.
Grey structure is the building itself: foundations, frame, slabs, brickwork, plaster and concealed services. Finishing is everything you see and touch afterwards: floors, paint, doors, windows, sanitary fittings, kitchen and wardrobes. Turnkey covers both.
As a guide from our own projects: design 3–4 weeks, working drawings 2–3 weeks, grey structure 4–6 months and finishing 2–3 months, or 8–12 months for a full turnkey design and build. Size, approvals and material selections change this.
Let’s build something meaningful.
Tell us about your plot and what you want built. Danial Khan reads every enquiry personally and replies with the next step.
Explore Danial Khan & Associates
Services
House designs
Cost guides
Company
Guides